Hello, here is my draft list of things that must be done at NTT.
  (List as of 29 July)

HPS room:
1.  Install 3 screens into each of 2 HPSes.
2.  Insure new pilot check valve is installed, if it isn't, get it installed.
3.  Remove orifice from 3rd main return valve.
4.  Use correct color brown paint on commoning tube between HPS 1 and 2.

Vertical Actuators:
1.  Install new LVDT rods.
2.  Replace Z1 and Z2 swivels, return old swivels to MTS America.
3.  Remove paint and counterbore for all swivels, top and bottom.

Table:
1.  Move accelerometers.
2.  Install new wings, insure all paint off of mating surfaces.

Controller:
1.  Update table.dat for new accelerometer location.
2.  Retune bare table.
3.  Do additional training.
4.  Redo bare table, 3g tests at vel/accel corner and at 40 Hertz. Do 50
	Hertz also but at the smaller specified g level.
5.  Redo Ito's diagonstic tests, i.e. measure transfer function, from  Z
	to mid point on Horizontal actuator and to table wing.  Hopefully peak
	resonance will be at 45+ Hertz with a multiplier of 5 or less.
6.  Try recreate the reported software errors from the last 2 months.
	Fix any that can be recreated.

Whole system:
1.  Touch up paint.
2.  Clean.


Any items that I missed?  Omar